Friday marked a major milestone for the Breckenridge Parking Structure team! Just 3 ½ months after breaking ground, the structure’s first pieces of precast are set and in place, ready for the 600+ pieces to follow. Considering the go-ahead for the project was still in limbo as recent as April, this is a huge accomplishment for all those involved. Not only was the team able to overcome an awkward and slow start due to COVID-19 and project approvals, they did so with a drive and passion that one can only hope for. The entire crew committed to the precast erection start date back in April, and thanks to a lot of coordination and hard work from each and every individual since, they were able to beat that commitment by 3 days. Congratulations to Lou O and Ian M and a special thank you to Rene R for getting things going. Onto the next milestone!