Dobson Ice Arena Ice Slab Pour

A major milestone for a community landmark.

Last Thursday, the Hyder McHugh team completed the ice slab pour at Dobson Ice Arena in Vail, marking an exciting step forward for a facility that means so much to the local community.

The pour included 300 yards of concrete placed over 10 inches of sand, multiple layers of vapor barrier, 4 inches of insulation, a hefty dose of rebar, and more than 14 miles of heated and cooled floor tubing. Completing a pour of this size in the heart of Lionshead Village during the busy summer season took careful planning, strong coordination, and a team that was ready to adapt when an I-70 closure delayed the start.

Congratulations and thank you to Arena Products, S2M, United Companies, Calco Concrete Pumping, the Town of Vail, Vail Recreation District, and the entire Hyder McHugh Dobson Ice Arena team for helping make this milestone a success.

Next up: the slab’s full 28-day cure, followed by continued work on rink-area equipment, devices, finishes, and painting as the project moves closer to substantial completion this fall.

Dobson Ice Arena | Town of Vail | Vail Recreational District | McHugh Construction

1031 Santa Fe Drive, Suite 300, Denver, CO 80204 | 303-825-1313 | Copyright 2021 Hyder Construction Inc. | Website by Small Giants, LLC

Privacy Preference Center